|
|
 |
Project History
 |
Project History |
 |
 |
 |
1980 |
 |
Proposals for a new publicly funded motorway |
 |
 |
1984 |
 |
Consultation on five route options |
 |
 |
1986 |
 |
Announcement of preferred route |
 |
 |
1988 |
 |
Public Inquiry on publicly funded scheme |
 |
 |
1989 |
 |
Announcement that the road will be built by the private sector. Private sector competition takes place |
 |
 |
1991 |
 |
Midland Expressway Ltd (MEL) announced as competition winner
MEL consults with the public
Alterations/alternative routes considered |
 |
 |
1992 |
 |
Concession Agreement signed by Government and MEL. Further alterations to route |
 |
 |
1994 |
 |
Public Inquiry on MEL scheme |
 |
 |
1995 |
 |
Public Inquiry ends |
 |
 |
1997 |
 |
Final go-ahead from Government |
 |
 |
1997 |
 |
Legal challenges against the scheme (Alliance against BNRR) |
 |
 |
1999 |
 |
Challenges cleared |
 |
 |
2000 |
 |
Competition for design and build contract |
 |
 |
2000 |
 |
MEL signs contract with CAMBBA for design and construction |
 |
 |
2000 |
 |
MEL signs contract for financing |
 |
 |
2001 |
 |
Minister announces name for road as M6 Toll |
 |
 |
2003 |
 |
Toll prices announced (6 May) |
 |
 |
2003 |
 |
M6 Toll opens (9 December) |
|
 |
Facts & Figures
 |
Contract |
 |
 |
 |
Contract Award/Effective Date |
 |
29th September 2000 |
 |
 |
Contract Period |
 |
40 Months |
 |
 |
Contract Value (Design and Construct) |
 |
£485m |
 |
 |
Contractor |
 |
CAMBBA (Carillion, Alfred McAlpine, Balfour Beatty, AMEC) |
 |
 |
Contractual completion |
 |
January 2004 (road opened 9 December 2003) |
|
 |
 |
Milestones |
 |
 |
Programme |
 |
 |
 |
Initial Site Clearance/Fencing Start |
 |
November 2000 |
 |
 |
Environmental Mitigation Works |
 |
November 2000 to March 2001 |
 |
 |
Archaeological Investigations |
 |
November 2000 to Spring 2001 |
 |
 |
Establishment of Main Project Offices |
 |
November 2000 to March 2001 |
 |
 |
Major Construction Activity |
 |
April 2001 to December 2003 |
|
 |
 |
Principal Quantities |
 |
 |
 |
Topsoil Strip |
 |
1,300,000 cubic metres |
 |
 |
Excavation(roughly the equivalent to 80,000double decker buses full) |
 |
9,200,000 cubic metres |
 |
 |
Fill(roughly the equivalent to 69,000 double decker buses) |
 |
7,500,000 cubic metres |
 |
 |
Excavated material processed(Drainage, pavement, concrete) |
 |
1,600,000 cubic metres |
 |
 |
Structural Concrete |
 |
63,000 cubic metres |
 |
 |
Steel Reinforcement |
 |
10,400 tonnes |
 |
 |
Formwork |
 |
90,000 square metres |
 |
 |
Reinforced Earth Panels |
 |
22,300 square metres |
 |
 |
Structural Steel (roughly the equivalent amount of steel used in the Eiffel Tower) |
 |
9,613 tonnes |
 |
 |
Road Construction |
 |
|
 |
Main Line |
 |
1,369,000 square metres |
 |
 |
Interchanges |
 |
184,000 square metres |
 |
 |
Side Roads |
 |
447,000 square metres |
 |
 |
Blacktop (Would fill over ten QE2 cruise liners) |
 |
800,000 tonnes |
 |
 |
Carrier Drains |
 |
139,000 metres |
 |
 |
Fencing/Hedges/Noise Barrier |
 |
165,000 metres |
 |
 |
Safety Fencing |
 |
130,000 metres |
 |
 |
Landscape Planting |
 |
4,430,000 square metres |
 |
 |
Structures |
 |
|
 |
Existing Bridges (20) |
 |
Widened 8
Demolish 4
Change 8

|
 |
 |
New Bridges (57) |
 |
Overbridges 34
Underbridges 12
Footbridges 5
Rail Bridges 3
Link Bridges 3 |
 |
 |
Culverts |
 |
Watercourses 41
Toll Tunnels 6 |
 |
 |
Retaining Structures |
 |
Walls 7
Strengthened Earth 4 |
 |
 |
Sign Gantries |
 |
68 |
 |
 |
Lighting Columns |
 |
2,500 |
 |
 |
Communications Cable |
 |
200,000 metres |
|
 |
|
 |


|
 |